Blair Hall & Adjacent Rock Lot Parking To Be Impacted by Upcoming Steam Plant Work Through October, November

BUILDINGS OR AREAS INVOLVED:  Blair Hall parking and rock lot by the old steam plant
DATE/TIME:  Sunday, October 13, 2024 – November 30, 2024
PURPOSE OF PROPOSED OUTAGE:  Smokestack demolition at the old steam plant
DETAIL:  The smokestack will be removed systematically and safely from the top down, knocking small pieces down the top of the stack and removing the rubble from the bottom until the structure is demolished down to the roofline of the old steam plant.  The rubble will be placed in trucks and hauled offsite for disposal.  Temporary fencing will be placed around the area and the entry by the water tower will be blocked off.  There will be construction noise and traffic.

 

Related Pages

Contact Information

Media Relations
Josh Reinhart,
Public Information Coordinator

Booth House
Eastern Illinois University
600 Lincoln Ave.
Charleston, IL 61920
217-581-7400
jdreinhart@eiu.edu


Take the next step

apply now
schedule a visit